Best Capacity Planning Software for Program and PMO Teams

33–50 minutes
Best Capacity Planning Software for Program and PMO Teams, featured image

Capacity planning software sets the hours your people can work against the hours your planned projects need, and shows the gap before you commit. For a program team the useful question is rarely who is free on Tuesday. It's whether the next project fits, which role runs out first, and what a hire would change.

We compared eight tools against those three questions. For each one we read the pricing page where one exists, a feature page, a help-center or documentation page showing how capacity, scenarios and overallocation work, and, for the rating, the review-site listing as of November 2026. We read vendor material and did not run these products. Where a mechanism isn't documented, the entry says so, because that's the question to put to the vendor in a demo. If you mainly need to book named people onto this week's work, our guide to resource management software covers that side.

capacity planning tools compared, from Float to Planview
8
sell by quote only (Workfront, Planview, Clarity)
3
Jira's lowest plan with Plans capacity and scenarios
Premium
resource seats Runn requires as a minimum
20

What is capacity planning software?

Capacity planning software is a tool that compares the hours your people can work with the hours your planned projects need and shows where demand outruns supply. It works on roles and teams over weeks and months, and it's about people, not servers or production lines.

Three kinds of tools sit under that name, and they answer capacity questions differently.

  • Resource schedulers (Float, Runn) put named people and roles onto projects by week and show who is overbooked.
  • Portfolio tools with capacity (Meisterplan, Celoxis, Planview, Clarity) check a ranked list of projects against the people you have before anything is approved.
  • Work management suites (Jira Plans, Workfront) keep capacity next to the tickets or tasks the teams already use.

Resource management books people onto work that's about to start, while capacity planning asks whether next quarter's work fits the people you'll have then. Most tools do both, so the entries below judge the forward-looking part. If you need to rank projects before you check capacity, our guide to project portfolio management software covers that layer.

Which capacity planning software is best?

No tool answers every question well. Pick by the question that's hardest for your program, then check the plan, because the cheapest tier often lacks scenarios. The plan table further down shows what each tier unlocks.

Three questions every capacity planning tool has to answer

Every capacity decision comes down to the same three questions. The entries below answer each one from vendor documentation under the headings absorbing a new project, finding where you run out of people and modeling one hire, and write "not documented" where a source is silent.

QuestionWhat the tool must showWhere tools fall short
Can we absorb project X?A tentative project or scenario that adds demand without touching confirmed workOnly confirmed bookings count, or the scenario can't be shared
Where do we run out of people?Demand against capacity by role and by week, with overload flaggedTeam totals hide one overbooked person
What does one hire change?A supply-side change shown against the same demandPlaceholders carry demand but no capacity

Capacity planning software compared

The table lists the tools from resource schedulers to enterprise portfolio platforms. Prices are USD per seat or user per month unless stated. Meisterplan lists its prices in euros, and "quote only" means the vendor publishes no figure.

ToolTypeScenario approachStarting price (USD unless stated)Rating
RunnResource schedulerTentative-project toggle, saved scenarios (beta), placeholders carry demand onlyLite $7, Standard $11 per resource seat (20 seats minimum) 4.8 (Capterra, 33)
FloatResource schedulerRole totals and overbooking alerts; tentative status and placeholders, no saved scenariosStarter $7, Pro $12 per scheduled person 4.5 (Capterra, 1,621)
MeisterplanPortfolio plannerPlan of Record copied into scenarios; role capacity added for hiresBasic EUR 600, Pro EUR 800 per month at 50 resources 4.7 (27)
CeloxisPortfolio managementHeat map and overload alerts; what-if is a manual project state with no undoCore $10 to Business $45 per user (5-user minimum) 4.6 (759)
JiraWork managementTeam capacity per sprint in Plans; individual Capacity view since July 2026Premium $15.56 per user at 300 users, monthly 4.3 (7,964)
Adobe WorkfrontEnterprise work managementResource Planner by role, user and project; Scenario Planner closed to new customersQuote only 4.1 (1,234)
PlanviewEnterprise portfolio managementRank, Analyze, Shift and Balance views against capacity targetsQuote only 3.8 (90)
Clarity (Broadcom)Enterprise portfolio managementRole and resource capacity; scenarios compared with the Plan of RecordQuote only 3.7 (91)
The Program Manager Our productCross-tool dependencies and milestone riskThe Program Manager maps dependencies across Jira and Asana, watches every milestone for risk, and keeps blockers, decisions and approvals in one graph.Team from $59 per workspace per month; card required at checkoutNo reviews yet

The 8 best capacity planning software tools

Each entry answers the three questions, names the plan that unlocks them, and ends with what reviewers report and who should skip the tool. Prices appear in the entry and once in the table.

Runn

Runn

Resource planner built around tentative projects and a scenario toggle, with per-seat prices and a 20-seat floor.

Resource planning and capacity forecasting 4.8 · 33 Capterra reviews

Runn fits a PMO or agency that wants to see utilization with and without pipeline work before it says yes to a project.

Absorbing a new project. Yes, and that's Runn's strongest answer. Mark a project tentative and a toggle in the charts includes or excludes its workload, so utilization appears with and without the pipeline. Saved scenarios go further: a scenario is a named set of tentative projects, and its capacity impact shows in the People Planner, the charts and the reports while confirmed work stays visible. Scenarios are in beta, private to the person who builds them and limited to project filters, so a PMO can't hand a colleague a scenario to review. Runn's help article lists them on Standard and Advanced, and the pricing page is less clear, so confirm Lite in a demo.

Finding where you run out of people. Capacity Insight can be filtered by role, and bars above the effective capacity line mean over capacity. Effective capacity is contracted hours minus time off, with public holidays handled automatically. The planner zooms from a week to a year and shows assignments in hours, FTE or capacity percent, so you're not locked into one unit.

Modeling one hire. Less than you'd hope. A placeholder carries workload but no capacity, though the help center lists supply-side scenarios as unsupported. The Hiring Proposals report lists placeholders marked Hire Proposed with effort in hours or FTE and exports to CSV, so it's useful for a hiring conversation, which gives you a hiring list, not a modeled gain in capacity. The placeholder resourcing-request workflow is Advanced only.

Runn charges $7 on Lite and $11 on Standard per resource seat per month, with at least 20 seats and a 30-day trial without a card. The BambooHR and Jira integrations and the API start on Standard.

Choose it when
  • You need to see utilization with and without pipeline projects before you commit, and the person who builds the scenario is the one who reads it
  • You want published per-seat prices and can commit to 20 resource seats
Skip it when
  • You need to model a hire as added capacity: placeholders carry workload only and supply-side scenarios aren't supported
  • You need SAML SSO or the placeholder resourcing-request workflow: both are Advanced only
Users like
a clear planner interface and responsive support
Users dislike
limited export options, an API call limit and limited reports and permission levels
Source: Capterra, 33 reviews
Runn People Planner with a scenario named High-Probability Projects switched on, an Edit Scenario panel with a probability filter, and department rows showing FTE free, Full or FTE over per week.
Runn People Planner with a saved scenario applied. Source: Runn capacity management page
Starting price
Lite $7, Standard $11 per resource seat per month, 20 seats minimum; Advanced by quote
Minimum
20 resource seats
Trial
30 days, no credit card
Scheduling unit
Hours per day, hours per week, FTE or capacity percent
Timesheets
Standard and up
SAML SSO
Advanced
Security
SOC 2 Type II
Scenarios
Beta; Standard and Advanced per the help article
Placeholders
Carry workload only, not capacity; unlimited on every plan; the Hiring Proposals report lists placeholders marked Hire Proposed
Forecast views
A week to a year, plus custom ranges
Hiring report
Hiring Proposals preset report, CSV export

Float

Float

Visual scheduler with role totals and overbooking alerts, but no saved scenarios and placeholders without capacity.

Resource scheduling and capacity planning 4.5 · 1,621 Capterra reviews

Float fits project teams that want to drag work onto a visual schedule, see overbooking at once and read role totals, without a heavy portfolio layer.

Absorbing a new project. Partly, though. Allocations carry a status of draft, tentative or confirmed, and tentative work shows as outlined tiles, so a team can lay a prospective project onto the schedule beside confirmed work. However, Float documents no saved scenario for comparing two versions of the plan, so each what-if lives on the live schedule and someone has to undo it.

Finding where you run out of people. That's Float's best answer. Capacity is the working hours a person has for project work after standard hours, approved time off and public holidays. Scheduling above a day's capacity turns the allocation red, and the People report counts overtime hours. The Roles tab of that report divides total scheduled hours, assigned and unassigned, by the capacity of the people in a role, and anything above 100 percent is overscheduled. Float's own example shows a copywriter role with 300 hours of capacity and 328 scheduled, or 109 percent.

Modeling one hire. Placeholders stand in for planned hires and can carry a role name, but they have no capacity of their own, so a placeholder adds demand and never supply. Starter allows one placeholder and Pro five; extra ones count as paid seats.

Starter costs $7 and Pro $12 per scheduled person per month. Pro adds time tracking, rate cards, project cost estimates, advanced reporting and SSO. Float connects directly with Asana, Jira, Teamwork and Trello, sends Slack notifications and has an API. No HR system connector is documented.

Choose it when
  • Your question is mostly who is overbooked and in which role, across many concurrent projects
  • You want scheduling, time tracking and cost estimates in one tool and can pay $12 per scheduled person for Pro
Skip it when
  • You need saved scenarios to compare two versions of the portfolio: Float documents tentative status and placeholders only
  • You plan a large hiring wave: placeholders carry no capacity and beyond five on Pro they cost seats
Users like
a clean, easy interface and a real-time view of who's working on what
Users dislike
limited reporting and customization, plus some mobile and calendar sync problems
Source: Capterra, 1,621 reviews
Float schedule for a designer showing a 129.2 percent utilization indicator and over-capacity warnings on days where booked hours exceed the day's capacity.
Float schedule with utilization indicators and over-capacity warnings. Source: Float capacity planning page
Starting price
Starter $7, Pro $12 per scheduled person per month; Enterprise by quote
Trial
30 days, no credit card; guests are free
Scheduling unit
Hours per day, percent of capacity or specific times
Placeholders
1 on Starter, 5 on Pro; extra ones count as paid seats
Time tracking and SSO
Pro
Rate cards
1 currency on Starter, 5 on Pro
Role supply and demand
People report, Roles tab: scheduled hours (assigned and unassigned) divided by the capacity of people in the role; over 100 percent means overscheduled
Scenarios
No saved scenario comparison documented; tentative allocations and placeholders model pipeline demand
Integrations
Asana, Jira, Teamwork, Trello, Slack notifications, API
Capacity unit
Hours per day, percent of capacity or set times
Role report
People report, Roles tab: scheduled hours divided by role capacity

Meisterplan

Meisterplan

Portfolio planner that copies the Plan of Record into scenarios, priced per schedulable person from 50 resources.

Project portfolio management (PPM) 4.7 · 27 G2 reviews

Meisterplan fits a PMO that has to decide which projects fit the people it has, and wants to test the answer in a copy of the plan before it changes the real one.

Absorbing a new project. That's what the tool is built around. One click copies the Plan of Record into a scenario, you add or shift projects there, and Meisterplan compares the scenario with the Plan of Record on schedule shifts, cost and effort. Approved projects, or the whole scenario, can be transferred back. Scenarios are unlimited and start on Pro, because Basic has none.

Finding where you run out of people. A resource's capacity comes from its calendar, absences and part-time model. The Team Planner highlights overallocation in its grid mode, and capacity reports, including a heat map, come with every edition. Demand can be assigned to a role before a named person exists, and the Team Planner helps spread the effort from the role across the available people.

Modeling one hire. A scenario can add capacity to a role, for example a plus-FTE change, to simulate a plan with extra people. The help center says a role has no capacity of its own, that such changes apply only to the scenario where you enter them, and that the added capacity counts toward license consumption.

Pricing is per resource, meaning a person who can be scheduled; users are free and unlimited. Meisterplan lists prices in euros: Basic EUR 600 and Pro EUR 800 per month at 50 resources, and Premium EUR 2,970 per month at 150, billed annually. Pro and Premium carry a mandatory one-time onboarding cost with no published amount, and the 30-day trial has Pro features. Pro adds the Jira, Asana and Wrike integrations; HR system connections need a custom integration.

Choose it when
  • You need what-if scenarios against capacity for a portfolio of 50 or more schedulable people
  • Your work lives in Jira, Asana or Wrike and you want a planning layer on top, which starts on Pro
Skip it when
  • You have fewer than 50 schedulable people: Basic and Pro start at 50 resources
  • You need to export plans freely: G2 lists import and export limits among its complaint themes
Users like
ease of use, project management, customer support and dashboards
Users dislike
data import, export limits and a learning curve
Source: G2, 27 reviews
Meisterplan Portfolio Designer with projects ranked by priority above a Must-Have line, a role capacity chart below and an overview panel for a selected project.
Meisterplan Portfolio Designer with role capacity below the ranked projects. Source: Meisterplan scenario planning page
Starting price
Basic EUR 600, Pro EUR 800 per month at 50 resources; Premium EUR 2,970 at 150; billed annually
Scenarios
Pro and Premium; unlimited
Capacity vs demand
Resource histogram of availability against demand; roles act as placeholders before named people are assigned; an allocation heatmap marks over-allocated (red) and under-allocated (blue) resources
Prioritization
Drag-and-drop ranking with a Must-Have line and a Cut-Off line; projects below the cut-off don't count against resources. Priority scoring with custom criteria on Pro and Premium
Financials
Estimate at Completion, CapEx and plan versus actual (vendor page)
Licensing
Per resource; users free and unlimited; teams aren't counted as resources
Integrations (vendor pages)
Jira (connector and side panel), Asana, Smartsheet, REST API; G2 also lists Azure Boards, Excel, Power BI, Power Automate
G2 rating
Not confirmed on the page read (27 reviews)
Role capacity
Roles have no capacity of their own; a capacity change entered on a role applies to one scenario and counts toward license consumption
Minimum
50 resources on Basic and Pro, 150 on Premium
Trial
30 days with Pro features
Onboarding
Mandatory one-time cost on Pro and Premium, amount not published
Currency
Prices are listed in euros

Celoxis

Celoxis

Portfolio tool with capacity on every plan and job roles from Essentials, but a manual what-if.

Project portfolio management (PPM) 4.6 · 759 G2 reviews

Celoxis fits a mid-size PMO that wants capacity, intake and portfolio reports on a published price ladder and can live with a manual what-if.

Absorbing a new project. Celoxis answers with a method rather than a button. The knowledge base has you create a What-if project state, put the new projects in it, filter the Resource Load view by that state and compare it with draft and active work. Reverting is manual, because Celoxis has no undo. The features page also describes ranking intake requests on KPIs and matching demand against capacity, and its FAQ lists intake management on Professional.

Finding where you run out of people. Allocation is a percentage of a resource's work hours or a fixed effort, and two 100 percent tasks in one week show a resource as overloaded on the Resource Load chart. The features page shows a capacity heat map by person and week, instant overload alerts and analytics by role, skill or custom field. The pricing table lists workload tracking and capacity planning on every plan from Core, while job roles, work calendars and instant resource conflicts start at Essentials. The features-page FAQ words that step more broadly, so check it in a demo.

Modeling one hire. Not documented. Celoxis's documentation describes roles and allocations but no hiring plan and no supply-side scenario.

Core costs $10, Essentials $25, Professional $35 and Business $45 per user per month billed annually, with at least 5 full-access users and a 14-day trial without a card. The Jira, Azure DevOps and QuickBooks Online connectors and Zapier are add-ons below Enterprise, and the integrations page lists a Microsoft Project import and a REST API.

Choose it when
  • You want capacity, intake and portfolio reports with prices you can budget before a demo
  • You test new projects against current resource load before approving them and accept a manual what-if
Skip it when
  • You want a tool teams adopt in days: G2 complaint themes are the learning curve and a complex interface
  • You need native copy-and-compare scenarios or a hiring plan: the documented what-if is a manual project state with no undo
Users like
project management, tracking, ease of use, time tracking and dashboards
Users dislike
a learning curve and a complex interface
Source: G2, 759 reviews
Celoxis capacity heat map by person and week with spare, booked and over-capacity legend and one person flagged at 124 percent in week 26.
Celoxis capacity heat map flagging one overloaded person. Source: Celoxis features page illustration
Starting price
Core $10, Essentials $25, Professional $35, Business $45 per user per month billed annually; Enterprise by quote
Program tier
Essentials, $25 per user per month (executive portfolio reporting)
Dependencies
All four types across projects, with lead and lag
Portfolio reports
8 built in
Resource workload and capacity
Workload tracking and capacity planning listed on every plan from Core; job roles, work calendars, timesheets and instant conflicts from Essentials
Optimal load
Admin sets a range (for example 80 to 90 percent); blue under, green optimal, red over-allocated
Auto vs manual scheduling
Each task is auto-scheduled or manually scheduled; auto tasks follow predecessors and the assignee's work calendar
Baselines
Every plan per the pricing table
Work calendars
Essentials and up
Intake
Requests from email, web forms and spreadsheets go into one queue and are ranked against your own KPIs; project intake management starts on Professional
Capacity
Workload is read across every project a person is booked on; capacity planning is listed on every plan from Core; job roles, work calendars, timesheets and resource-conflict visibility from Essentials
Financials
Budgets at project and task level, job-role rates, planned versus actual by project and portfolio; expenses and costing from Professional, billing from Business
Seats
Minimum 5 full-access users; read-only users free; 14-day free trial, no credit card
Integrations
Jira, Azure DevOps, QuickBooks and Zapier are add-ons below Enterprise
Scenario planning
The features page names what-if analysis under request tracking and gives no detail
What-if
Manual project state, no undo
Minimum
5 full-access users
Trial
14 days, no credit card
Capacity by plan
Pricing table: from Core; roles, calendars and instant conflicts from Essentials

Jira

Jira

Sprint capacity and scenarios inside Jira Plans, plus a weekly per-person view, all from Premium.

Agile program planning 4.3 · 7,964 G2 reviews

Jira fits a program whose delivery teams already plan in Jira and want sprint capacity next to the issues, if the organization can pay for Premium.

Absorbing a new project. Plans, formerly Advanced Roadmaps, includes scenarios: a what-if copy of a plan whose changes aren't written to Jira work items until you save them. Scenario modeling is a Premium and Enterprise feature. How capacity behaves inside a scenario isn't covered in Atlassian's scenario documentation.

Finding where you run out of people. Two mechanisms exist, and they don't overlap. In Plans, capacity is per team and per sprint, in story points or hours, and defaults to 30 story points. Each team swimlane shows a bar that turns red when assigned work exceeds capacity. Plans divides a team's capacity equally across its members, and a partner answer on Atlassian's community forum says Plans doesn't flag individual overallocation. The second mechanism is the Capacity view that Atlassian announced on July 27, 2026: a weekly grid of each person's allocations in percent, hours or days, with a red bar above 100 percent. It uses a fixed 40-hour week, and allocations over 100 percent are flagged, not blocked.

Modeling one hire. Not documented for either mechanism, and role or skill based capacity isn't described either.

Capacity, scenarios and the Capacity view all need Premium, which was $15.56 per user per month at 300 users on the monthly toggle; Atlassian's price per user changes with team size. The plan has to use boards as its work sources and issues need estimates, because work pulled in through spaces or filters shows no capacity.

Choose it when
  • Your teams already estimate in Jira and you want sprint capacity and a cross-team timeline in one place
  • You have Premium or can move there: Plans capacity, scenarios and the Capacity view all sit on that tier
Skip it when
  • You're on Free or Standard: capacity management, scenarios and Plans are Premium and Enterprise features
  • You need role or skill based supply against pipeline demand: it isn't documented, and team capacity splits equally across members
Users like
ease of use (1,157 mentions in G2's pros summary) and flexibility (857)
Users dislike
the learning curve (682 mentions), interface complexity (504), difficulty for new users (455), feeling overwhelmed (344) and slow performance on large projects (327); the first four overlap
Source: G2, 7,964 reviews
Jira Plans sprint capacity flyout for Stagehand Sprint 4 showing 26 of 50 days allocated and a note that 3 issues are not assigned to a sprint.
Jira Plans sprint capacity flyout. Source: Atlassian support documentation
Starting price
Free for 10 users; at 300 users billed monthly Standard $8.48, Premium $15.56 per user per month; Enterprise by quote
Program tier
Premium, $19.60 per user per month (monthly, 10 to 100 users); annual 10 users $1,950 per year
Dependencies
Single project on Free and Standard, cross-project on Premium and Enterprise
Automation
Free 150 steps per subscription, Standard 400, Premium 750, Enterprise 1,000 steps per user per month
WIP limits
Min and max per column; header turns red or yellow, moves are not blocked
Trello import
Official importer; archived cards, checklists and custom fields not imported in software spaces
Other reviews
TrustRadius 8.4 of 10 (4,390 ratings), Software Advice 4.4 of 5, checked 2026-10-26
SSO and SCIM
Atlassian Guard Standard; included with Enterprise, a separate subscription on Standard and Premium
Data residency
Standard, Premium and Enterprise; regions include US, EU, UK, Canada, Australia, India, Japan, Singapore, Germany, Switzerland, South Korea
Strategy Collection
Focus and Jira Align; needs Jira Cloud Premium or higher
Enterprise
Contact sales; 99.95% uptime guarantee
Data Center
End of sale for new customers March 30, 2026, for existing customers March 30, 2028, end of life March 28, 2029; Server support ended February 15, 2024 (Atlassian)
Price update
List prices rose again on October 13, 2026: Standard $9.05 to $9.70, Premium $18.30 to $19.60 per user per month (1 to 100 users); Atlassian's 2025 increase was 5 percent Standard, 7.5 percent Premium
Free plan
Up to 10 users, 2 GB storage, 150 automation steps per subscription per month, community support
Export
CSV export of up to 10,000 work items at a time; Backup manager includes attachments only if ticked, with 48 hours between backups with attachments; automation flows and app data are not in the backup
Capacity in Plans
Per team and sprint, story points or hours, default 30 points
Capacity view
Weekly grid per person, fixed 40-hour week, announced July 27, 2026
Plan needed
Premium or Enterprise
Work sources
Boards only; spaces and filters show no capacity

Adobe Workfront

Adobe Workfront

Role, project and user capacity views with budgets up to 15 years ahead, and a scenario tool closed to new buyers.

Enterprise work management for marketing and creative teams 4.1 · 1,234 G2 reviews

Adobe Workfront fits an enterprise that already runs work in Workfront and wants role-level capacity against budgets, and that doesn't need to buy scenario planning new.

Absorbing a new project. Workfront's Scenario Planner models this. Plans define the supply of people and budget, initiatives define the demand, and when they conflict you change initiative demand, priorities or the supply on the plan. Several scenarios can be built and compared, and publishing one updates linked projects. The access documentation says it needs the Ultimate package and is no longer available for purchase to new customers, while the feature page says it needs a separate license. Adobe community posts call it a forgotten function, and one user reports being told in 2024 that it isn't being actively developed. We found no Adobe statement either way, so ask what's planned before you count on it.

Finding where you run out of people. Resource Planner works in role, project and user views. It shows available, planned, budgeted and net hours, in hours, FTE or cost, by week, month or quarter. Net is available minus budgeted, or minus planned if you switch that on, and red marks overallocation. The user allocation chart shows overallocated users in red and underutilized users in blue. Budgeting runs up to 15 years ahead, with a week as the smallest period. A role with no users shows zero available hours, and the role view counts only work assigned to a role or to someone who holds it.

Modeling one hire. Through Scenario Planner, where supply can change on a plan. Without it you'd budget extra hours for the role in Resource Planner instead.

Select, Prime and Ultimate are sold by quote, and Adobe publishes no price. Resource Planner is available in any package, and Workfront Fusion is a separate low-code connector sold as an add-on.

Choose it when
  • You already run on Workfront and need available, planned and budgeted hours by role for a week, month or quarter
  • You plan budgets years ahead: Resource Planner budgets up to 15 years
Skip it when
  • You're a new customer who needs scenario planning: Adobe's access page says Scenario Planner is no longer available for purchase
  • You want a price before a sales call or a light rollout: G2 reviewers name the learning curve and a tool that isn't intuitive
Users like
project management and ease of use
Users dislike
learning curve and not intuitive
Source: G2, 1,234 reviews
Adobe Workfront Resource Planner view by user, with available, planned, actual and difference hours per month for each person and week, month and quarter buttons.
Workfront Resource Planner by user. Source: Adobe Experience League documentation
Starting price
Select, Prime and Ultimate by quote; no public price
Plans
Select, Prime and Ultimate; Prime adds advanced work management and security, Ultimate adds enhanced automation and data management
Portfolio management
Prime and Ultimate; not in Select
Review and approval
Listed in all three plans; advanced proofs allow guest reviewers without a Workfront login, optional login, e-signature and locking
Creative Cloud
Comments and approvals inside InDesign, Illustrator, Photoshop, XD, Premiere Pro and After Effects via an Adobe Exchange add-in
Intake
Request queues with custom forms and auto-routing, listed in all three plans
Resource management
Project-level and global allocation, listed in all three plans; depth per tier not confirmed
Dependencies
Task predecessors with lag, cross-project predecessors and a Gantt view
Client seat rule
Not confirmed for the core app; proof guest reviewers need no login
Billing
Billing records track billable hours and expenses; Workfront doesn't issue invoices
Retainers
No retainer feature found
Connectors
Slack, Microsoft Teams and Figma through Workfront Fusion, a separate licence
Portfolio Optimizer
A project request carries a Business Case; the portfolio manager reviews it, then ranks projects in the Portfolio Optimizer by value, alignment, financials, scorecard and ROI, checks resources, and approves with a baseline
Portfolios and programs
A portfolio is a collection of projects with common goals; a program belongs to exactly one portfolio and a project links to one program at a time; the Optimizer can't compare projects inside a single program
Scenario Planner
Ultimate package; closed to new customers per Adobe's docs
Portfolio budget
Entered manually at portfolio level
G2 implementation time
4 months on average, 14 months to ROI
Integrations (docs)
Adobe Experience Manager Assets, Jira, Salesforce, Slack, Google Workspace, Creative Cloud; Fusion is a separate low-code connector
Resource Planner
Role, project and user views; hours, FTE or cost; week as smallest period
Packages
Select, Prime, Ultimate; quote only
Horizon
Budgeting up to 15 years

Planview

Planview

Enterprise portfolio tool that checks demand against capacity targets in four ordered views, sold by user band.

Project portfolio management (PPM) 3.8 · 90 G2 reviews

Planview Portfolios fits a large PMO that decides which investments to fund by checking demand against capacity and budget, and has the admin team to run it.

Absorbing a new project. Planview's Planning Manager walks through four views in order. Rank sorts investments by scoring criteria. Analyze moves investments above or below the funding line and shows the effect on budget and capacity. Shift shows where demand exceeds capacity by period and lets you shift investments to fit. Balance shows the time-profiled impact of accepted investments against capacity and budget targets. Planview's documentation warns that what-if work on the Shared Scenario is easy to do by accident, and user scenarios change nothing in the financial plan until you publish them.

Finding where you run out of people. Capacity is set as time-phased resource capacity targets that Planview compares with demand from the forecast of work in the portfolio. The resource management capability tracks vacations and absences, identifies over- and under-allocated resources and measures demand by role classification. Demand that is pending approval or outside the planning horizon is left out of the analysis. A maximum horizon isn't documented.

Modeling one hire. No dedicated hiring plan is documented. The Balance view can model changes to defined capacity, but Planview's documentation doesn't say whether that covers a hire.

Planview publishes no price, but the Planning Package is sold by Portfolio Management FLEX users: Base up to 50, Standard up to 100 and Custom above that, with a fixed-price FastTrack implementation. Reporting and FLEX Sandbox are add-ons, and the edition that unlocks scenarios isn't named. Jira, Azure DevOps, ServiceNow and Microsoft Project Server connect through Planview Hub; whether Hub is included isn't documented.

Choose it when
  • You fund and prioritize many initiatives and need to see demand against capacity before approving them
  • Agile teams stay in Jira while leadership plans in a portfolio tool, connected through Planview Hub
Skip it when
  • You have fewer than a few dozen planners or need a published price: packages start at a 50-user band and are sold by quote
  • You want a quick rollout: PeerSpot reviewers say configuration needed external consultants and end users find the product hard to work with
Users like
project and resource management, tracking and reporting
Users dislike
a long support ticket process and a UX that needs rework
Source: G2, 90 reviews
Planview Planning Manager Shift view with ranked investments, demand above capacity marked in red by period and a bottom tray comparing demand with capacity by resource role.
Planview Planning Manager Shift view. Source: Planview documentation, an older release
Starting price
Quote only; Planning Package by user band (Base up to 50, Standard up to 100, Custom above)
Packages
Base up to 50, Standard up to 100, Custom above, by Portfolio Management FLEX users
Reporting
Embedded Power BI; Reporting add-on
Lighter option
Planview AdaptiveWork (formerly Clarizen)
SAML SSO
Via Planview Admin, IdP and SP initiated (Entra ID, ADFS, Okta, OneLogin); plan tier not stated in docs
Trust Center (Oct 2026)
ISO/IEC 27001, ISO/IEC 27701, SOC 2, CSA STAR, GDPR
Integrations (product page)
SAP, NetSuite, Oracle ERP, Salesforce, Workday, ServiceNow, Atlassian, Microsoft; Jira through Planview Hub
Demand management
Collects demand from unstructured ideas to formal program and project requests
Investment prioritization
Rank view sorts investments by scoring criteria; rankings can be applied automatically by criteria, set manually by scenario users, or both
Scenarios
Shared scenario plus user scenarios, published when ready
Capacity vs demand
Compares available capacity, either resource capacity or a financial budget, with demand from the portfolio work forecast; demand with a Pending approval status or outside the planning horizon is excluded
Reports
More than 200 out-of-the-box reports and visualizations
Jira and Azure DevOps
Through Planview Hub toolchain integrations, not described as native Portfolios integrations
Capacity views
Planning Manager: Rank, Analyze, Shift (where demand exceeds capacity by period) and Balance
Views
Rank, Analyze, Shift and Balance
Add-ons
Reporting and FLEX Sandbox

Broadcom Clarity

Clarity (Broadcom)

Enterprise portfolio platform with role capacity, hard and soft bookings and scenarios against the Plan of Record.

Project portfolio management (PPM) 3.7 · 91 G2 reviews

Broadcom Clarity fits a large IT or portfolio office with admin support that wants capacity, demand and funding on one governed record.

Absorbing a new project. Clarity's capacity planning scenarios make temporary changes. You can modify team allocations, move investment start dates, switch investments between approved and unapproved, or add investments, then compare the scenario with the Plan of Record or another scenario, with the differences shown in red. Some data is read-only in scenario mode, and only some fields are editable in scenario properties. Broadcom's scenario documentation describes the Classic UI of version 16.2, so check the Modern UX in a demo.

Finding where you run out of people. Broadcom's older documentation defines capacity as the time a resource makes available and demand as requested time on a resource or role, split into hard-booked and soft-booked time. Unused capacity below zero means over-allocation. The resource planning pages offer a role capacity histogram, unfilled allocations and workload views, from organization-wide totals down to booking detail. A July 2026 thread on Broadcom's community site reports that roles used as placeholder demand also add to capacity in Modern UX reports on version 16.4.1, which overstates it. Broadcom's reply says release 16.3.2 added a system option to hide role contributions.

Modeling one hire. A dedicated hiring plan isn't documented. Roles act as placeholder demand, and scenarios let you change team allocations.

Broadcom publishes no price, edition page or minimum, and it doesn't say which edition has scenarios. Reviewers on PeerSpot describe setups of three to six months, name cost as a concern and call the Jira connection cumbersome.

Choose it when
  • A large IT or portfolio office wants governed intake, funding decisions and capacity scenarios on one record
  • You have admins or configuration partners and can run an implementation measured in months
Skip it when
  • You're a small team or want a published price: Broadcom lists none, and G2 reviewers name cost and a steep learning curve
  • Your delivery data lives mostly in Jira: PeerSpot reviewers call that integration cumbersome
Users like
customization, ease of use and time tracking
Users dislike
cost and a steep learning curve for advanced features
Source: G2, 91 reviews
Broadcom Clarity project properties page for a data warehouse project with a Scenario selector in the page header next to the Actions menu.
Clarity project page with a Scenario selector, Classic UI. Source: Broadcom documentation, version 16.2
Starting price
Quote only; Broadcom lists no price or editions
Former names
CA PPM, Clarity PPM
Portfolio plans
A plan is a what-if copy of portfolio data with start and finish dates and cost, resource and benefit targets; versions compare on a Waterline view where projects above the line are funded; one version becomes the Plan of Record
Capacity scenarios
Temporary versions of a plan: change team allocations, shift start dates, switch investments between approved and unapproved, then compare against another scenario or the Plan of Record with the differences marked
Financial planning
Investment planning, cost accounting, forecasting and automated software capitalization (vendor page)
Roadmaps
Interactive drag-and-drop roadmaps and scenario modeling (vendor page)
Deployment
SaaS and on-premises documentation both exist
Customer size (PeerSpot reviewers)
92 large enterprise, 9 midsize, 15 small business
Implementation (PeerSpot reviewers)
One reviewer says 3 to 6 months, another up to 12 months for complex setups; many used consultants or partners
Priority scoring
The docs read do not explain how priority scores are calculated
Integrations (vendor page)
Rally, ConnectALL and Insights from Broadcom ValueOps; Jira, SAP and ERP connectors not confirmed on vendor pages
Roles as placeholders
July 2026 community thread: can inflate capacity reports on 16.4.1
Capacity model
Capacity is time made available; demand is hard-booked plus soft-booked time
Scenarios
Compared with the Plan of Record; some fields read-only
Other reviews
PeerSpot 4.0 of 5 from 143 reviews

Which plan unlocks scenarios and capacity views?

Capacity views are rarely the paywalled part, but scenarios and role-level views often are. The table names the lowest tier where each capability is documented, and "not documented" means the vendor's own pages don't say.

ToolCapacity viewsScenariosRole-based demandModeling a hire
RunnLiteStandard per the help article; tentative toggle on LitePlaceholders, unlimited on every planPlaceholders carry no capacity
FloatStarterNot documentedRoles report; 1 placeholder on Starter, 5 on ProPlaceholders carry no capacity
MeisterplanBasicProRoles; the role capacity article covers all editionsRole capacity change inside a scenario (Pro)
CeloxisCore per the pricing tableManual What-if state, plan not documentedJob roles from EssentialsNot documented
JiraPremiumPremiumNot documentedNot documented
WorkfrontResource Planner in any packageUltimate package, closed to new customersRole viewSupply change inside Scenario Planner
PlanviewNot documented by editionNot documented by editionRole classificationsNot documented
ClarityNot documented by editionNot documented by editionRoles as placeholdersNot documented

Meisterplan shows the staircase most clearly, because each tier changes what a PMO can do with it.

Meisterplan
  1. BasicTeam Planner, Resource Pool, capacity reports with heat map and absence management, from 50 resources; no scenarios
  2. ProScenarios, portfolio dashboard, prioritization, financials, and the Jira, Asana and Wrike integrations; onboarding cost is mandatory
  3. PremiumFrom 150 resources, annual payment only, a dedicated customer success manager, Entra ID auto-provisioning and a self-service sandbox

What is the process of capacity planning?

Capacity planning is a loop of five steps, and the software only automates the arithmetic. Doing it once by hand shows what the tools calculate.

  1. List supply by role

    Count the hours each role can give to projects after leave, public holidays and non-project time such as support or meetings.

  2. List demand

    Add the hours each confirmed project needs from each role, and keep tentative projects in a separate column.

  3. Find the gap

    Divide demand by supply for each role and month. Above 100 percent means the plan doesn't fit.

  4. Test scenarios

    Move a start date, drop a project, or add capacity for a hire, and read the gap again.

  5. Decide and revisit

    Commit to one plan, tell the project owners what moved, and repeat the check when a project or a person changes.

The example below uses five backend engineers over one month.

LineHours per monthNote
Gross hours, 5 engineers at 160800Supply before deductions
Leave and holidays-8010 working days
Non-project time, 20 percent of the remaining 720-144Support and meetings
Project capacity576115.2 hours per engineer
Project A, confirmed300
Project B, confirmed200
Confirmed demand50087 percent of capacity
Project C, tentative160
Demand with Project C660115 percent of capacity
Gap if C goes ahead84About 0.7 of one engineer

The confirmed work fits with 76 hours to spare, but adding Project C overshoots by 84 hours. You can move C, drop part of A or B, or add about 0.7 of an engineer. That last choice is the third question in the tools above.

A capacity planning model is the rule you follow when supply and demand differ. You can add capacity ahead of expected demand, add it only after demand shows up, or add it in small steps as demand grows. Tools help most with the second and third, since they show the gap early enough to act on it.

How to choose capacity planning software

Choosing is the smaller job. Most plans fail because the inputs are wrong, not because the tool is: leave isn't entered, estimates are guesses, and nobody owns the weekly update. Decide who maintains the data before you compare tools, then match the tool to the hardest of the three questions. Don't start with the demo that looks best. If your program also needs a view of schedule risk across projects, the project scheduling software guide covers that side.

  • You want utilization with and without pipeline projects, and the planner also reads the resultRunn
  • A team needs a visual schedule with role totals and the pipeline is smallFloat
  • A PMO has 50 or more schedulable people and needs scenarios against a Plan of RecordMeisterplan
  • You need capacity and intake on published prices and accept a manual what-ifCeloxis
  • Delivery teams estimate in Jira and the organization pays for PremiumJira
  • You already run on Workfront and plan hours by role and budgetAdobe Workfront
  • A large PMO funds initiatives and checks demand against capacity before approvalPlanview
  • An IT portfolio office with admin support compares scenarios with a Plan of RecordClarity (Broadcom)
Capacity planning software checklist
  • Name who keeps leave, hours and project estimates current, and how often
  • Pick your hardest question: a pipeline project, one overloaded role, or a hire
  • Ask the vendor to show that question on screen with your own tentative project
  • Find the plan that holds scenarios and role views, and note seat or resource minimums
  • Check whether a placeholder can carry capacity, or only demand
  • Check which tools it connects to (Jira, Asana, an HR system) and which plan has the connector
  • Ask what happens to a scenario when the live plan changes, and who can see it

Is there free capacity planning software?

None of the eight tools lists a free plan that includes capacity planning. Jira has a Free plan for up to 10 users, but capacity management and scenario modeling start at Premium. Trials are the practical route: Float and Runn give 30 days without a credit card, Meisterplan gives 30 days with Pro features, and Celoxis gives 14 days without a card. For a first pass, the supply and demand table in the process section works in any spreadsheet.

Where The Program Manager fits

The Program Manager doesn't do capacity planning, and it isn't a ranked entry here. It doesn't hold calendars, hours or utilization, so it doesn't replace any tool above. It sits next to one. If your delivery work lives in Jira and Asana, it maps the dependencies between the two, watches milestones for risk and keeps blockers, decisions and approvals in one graph. A capacity tool shows that a role is overbooked in March. The graph shows which milestones depend on the work that role owns.

FAQ

What are some effective tools for resource capacity planning?

Effective tools for resource capacity planning include Runn, Float, Meisterplan, Celoxis, Jira Premium, Adobe Workfront, Planview and Broadcom Clarity. Float and Runn start at $7 per seat per month, Celoxis at $10 per user, Jira's capacity features need Premium, and Workfront, Planview and Clarity are sold by quote.

What is the process of capacity planning?

The process of capacity planning has five steps: list supply by role after leave and non-project time, list confirmed and tentative demand, divide demand by supply to find the gap, test scenarios such as moving a project or adding a hire, then commit and revisit when something changes. In a worked example, five engineers with 576 project hours face 660 hours of demand once a tentative project is added, which is 115 percent.

What is a capacity planning model?

A capacity planning model is the rule for matching supply to demand. You can add capacity ahead of expected demand, add it only after demand appears, or add it in small steps as demand grows. Scenario tools let you test each choice against the same demand.

What is the best capacity planning software?

The best capacity planning software depends on the hardest question. Runn is the clearest on pipeline what-ifs, Float on role totals and overbooking, Meisterplan on portfolio scenarios, and Jira Premium for teams that already estimate in Jira. Workfront, Planview and Clarity suit large organizations that buy by quote.

Is there free capacity planning software?

Free capacity planning software is rare: none of the eight tools lists a free plan with capacity planning. Jira's Free plan covers up to 10 users but excludes capacity management and scenarios. Float and Runn offer 30-day trials without a card, Meisterplan 30 days and Celoxis 14 days.

What is the difference between capacity planning and resource management?

Resource management books named people onto work that is about to start. Capacity planning compares the hours your people will have with the hours planned projects need, usually weeks or months ahead, and shows where you run out. Most tools do both.

Stop guessing. Start knowing what will slip.