RAID Log Template: Free Excel and Word Download for Programs

16โ€“23 minutes
RAID Log Template: Free Excel and Word Download for Programs, featured image

A RAID log template is a ready-made spreadsheet with one row per risk, assumption, issue or dependency and a fixed set of columns: ID, type, description, workstream, owner, probability, impact, score, response, status and two dates. The one below is filled in for a fictional point-of-sale rollout across a retail chain, with nine example entries you can overwrite.

Copy it into a sheet or download it as an Excel or Word file, whichever you'll actually use. The Excel file has dropdowns for type and status, a score formula and a red flag on overdue reviews. If you need the definition of RAID first, our RAID log guide explains it. This page is for the moment you've got to produce the file. It's free, and there's no sign-up.

RAID log template at a glance
  • Copy or download the log below, replace the example entries and delete the rows you don't use. Twelve columns are included, and six of them are the minimum.
  • Give every entry an ID, a type, one named owner, a status and a review date. A log without review dates is a list nobody reopens.
  • Score risks as probability times impact on 1 to 5 scales, so the top score is 25. Issues have already happened, so they get an impact and no probability.
  • On a program, keep one identical log per workstream and move only escalated entries and cross-workstream dependencies into a program log.

Free RAID log template: copy it or download it as Excel or Word

The RAID log template has 3 tabs and 12 columns. Tab 1 is the RAID log, with 9 example entries from a fictional point-of-sale rollout: two risks, two assumptions, two issues and three dependencies. Tab 2 holds the lists and scoring rules behind the dropdowns. Tab 3 lists six checks and the plain COUNTIFS formulas that run them. Everything in it is an example, so you'll want to replace the entries, names and dates with your own.

Template

RAID log template for a program

Three linked tabs: a RAID log filled in for a fictional point-of-sale rollout across a retail chain, a tab with the lists and scoring rules, and a tab of checks. Every entry, name and date is an example. Replace them with your own and delete the rows you don't use.

Tab 1: RAID log
IDTypeDescriptionWorkstreamOwnerProbabilityImpactScoreResponseStatusDate raisedReview date
R-01RiskIf the card terminal vendor ships after 14 December, the 12 pilot stores can't go live before the holiday freezeHardwareHardware lead3515Ask the vendor for a firm ship date and line up the backup terminal modelEscalated2026-11-022026-11-23
R-02RiskTwo trainers may be pulled onto the January stock countTrainingTraining lead339Book the trainers for the pilot weeks nowOpen2026-11-022026-11-30
A-01AssumptionStore Wi-Fi can carry the new till software without upgradesHardwareProgram managern/an/an/aSurvey six pilot stores by 27 NovemberOpen2026-11-022026-11-27
A-02AssumptionFinance approves the new receipt layout within three weeksSoftwareSoftware leadn/an/an/aSubmit the layout by 9 November and check at the next reviewOpen2026-11-022026-11-30
I-01IssueThe test payment gateway rejects refunds, so returns can't be testedPaymentsPayments leadn/a4n/aRun the manual refund script while the vendor ticket is openOpen2026-11-092026-11-16
I-02IssuePilot store 3 has no network port at the tillHardwareHardware leadn/a2n/aElectrician booked for 18 NovemberResolved2026-11-092026-11-23
D-01DependencyTill software testing needs the new product catalog from merchandisingSoftware, needs MerchandisingProgram managern/an/an/aDelivery date requested from the merchandising leadOpen2026-11-022026-11-16
D-02DependencyTraining videos need the final screens from designTraining, needs DesignTraining leadn/an/an/aFinal screens due 30 NovemberOpen2026-11-022026-11-30
D-03DependencyPilot go-live needs the card terminals tracked in R-01HardwareProgram managern/an/an/aLinked to R-01, review togetherEscalated2026-11-022026-11-23
Tab 2: Lists and scoring
FieldAllowed valuesRule
TypeRisk, Assumption, Issue, DependencyOne type per row. When a risk happens, log a new issue and keep the risk's ID in the response.
StatusOpen, Escalated, Resolved, ClosedResolved means the work is done. Closed means someone confirmed it at a review.
Probability1 rare, 2 unlikely, 3 possible, 4 likely, 5 almost certainRisks only. Issues have already happened.
Impact1 minor, 2 small, 3 moderate, 4 major, 5 severeRisks and issues. Use the same scale in every workstream.
ScoreProbability times impact, 1 to 25Risks only. Formula in the Excel file.
Bands (example)1 to 7 low, 8 to 14 medium, 15 to 25 highOur example thresholds. Agree your own with the steering committee.
IDType letter plus number, such as R-01Add a workstream prefix for a program, such as HW-R-01.
Tab 3: Checks
CheckPass conditionFormula (log in rows 2 to 200, columns as in Tab 1)
Entries without an owner0=COUNTIFS(B2:B200,"<>",E2:E200,"")
Open or escalated entries past their review date0=COUNTIFS(J2:J200,"Open",L2:L200,"<"&TODAY())+COUNTIFS(J2:J200,"Escalated",L2:L200,"<"&TODAY())
Risks without a response0=COUNTIFS(B2:B200,"Risk",I2:I200,"")
High risks (score 15 or more)Each one escalated or has a named reason=COUNTIFS(B2:B200,"Risk",H2:H200,">=15")
Resolved entries still waiting for a reviewClosed at the next review=COUNTIFS(J2:J200,"Resolved")
Open risksCompare with last review=COUNTIFS(B2:B200,"Risk",J2:J200,"Open")
Download as Excel (.xlsx)Download as Word (.docx)Free, no sign-up. Use Copy as text to paste a tab into Google Sheets.

How to read the example: R-01 scores 15 and is escalated because the whole pilot depends on the card terminals. D-03 is the dependency side of the same problem, so the two entries are linked and reviewed together. The assumptions each carry a check, since an assumption nobody plans to validate is just a risk nobody has named. I-02 is resolved but not closed, which is intentional: it stays on the log until the next review confirms the port works.

Cells that read n/a aren't gaps. A probability doesn't apply to an issue because it has already happened, and an assumption gets no score at all. Leave those cells empty in your own log. The check formulas still work, but a stray zero would throw them off.

What should a RAID log template include?

A RAID log template needs 6 fields at minimum: an ID, the type, a description, one owner, a status and a review date. The other 6 in the file (workstream, probability, impact, score, response and date raised) turn it from a list into a log you can run a program with. Add contingency only if your risks need a separate fallback plan.

ColumnWhat to writeApplies toNeeded from day one
IDA unique number with a type letter, such as R-01 or D-03AllYes
TypeRisk, assumption, issue or dependencyAllYes
DescriptionOne sentence: the condition and what it affectsAllYes
OwnerOne named person who keeps the entry movingAllYes
StatusOpen, escalated, resolved or closedAllYes
Review dateThe day someone must look at it nextAllYes
WorkstreamThe project or team the entry belongs toAllPrograms
Probability1 to 5RisksOptional
Impact1 to 5Risks and issuesOptional
ScoreProbability times impactRisksOptional
ResponseThe mitigation, validation step, workaround or the date you're waiting forAllYes, for anything scoring 8 or more
Date raisedThe day the entry was addedAllOptional
ContingencyWhat you'll do if the risk happensRisksOptional

The column set follows what the published templates ask for, and it's much shorter than most people expect. Smartsheet's basic RAID template has columns for the RAID category, description, impact and priority. Career Smarter's template has 10 columns: ID, type, description, owner, impact, probability, status, actions, date raised and review date. Smartsheet also says every item should carry its category, an ID number, a deadline, a description and an assignee. Cafe Associates keeps contingency apart from mitigation and points out that likelihood doesn't apply to issues.

Asana's template cuts it differently: it separates the log into risks, assumptions and dependencies found during planning, and issues, actions, dependencies and decisions raised after kickoff. If your project already has a kickoff date, a column for the phase in which the entry was raised does the same job inside one sheet.

How do you fill in a RAID log template?

Fill in a RAID log template by gathering the entries as a team, writing each one as a single sentence, giving it an ID and one owner, scoring the risks and setting a review date. Atlassian suggests workshops, stand-ups or focused discussions to collect the first list, because individual contributors miss things others see. The five steps below add the scoring and the review rhythm.

  1. Collect the first entries as a team

    Bring the project leads, and for a program the workstream leads and the PMO, into one session. Ask three questions: what might go wrong, what are we treating as true without proof, and what do we need from another team. Log everything before you argue about scores.

    Owner: program manager
  2. Write each entry as one sentence

    Use the pattern "If X happens, Y is affected" for risks and a plain statement of what's broken for issues. Vague entries such as "vendor problems" can't be scored, assigned or closed, and they're the first ones people stop reading.

    Owner: whoever raises the entry
  3. Give every entry an ID and one owner

    Cafe Associates advises numbering each entry, because names alone get confusing when you refer back to them. The owner is the person who keeps the entry moving, not necessarily the person who fixes it.

    Owner: program manager
  4. Score the risks and write the response

    Rate probability and impact from 1 to 5 and let the formula multiply them. Anything scoring 8 or more gets a response with a date. Issues get an impact and a workaround, and dependencies get the date you're waiting for.

    Owner: entry owners
  5. Set a review date and keep it

    Every entry needs a date when someone must look at it again. Rebel's Guide to Project Management reviews dependencies about once a month and suggests reviewing everything on the log at least monthly. Fast-moving programs usually review weekly.

    Owner: workstream leads
Five steps to fill in a RAID log template: collect, write, assign an ID and owner, score and respond, set a review date.
Collect first, score second, and never leave an entry without a review date.

How do you score risks and set up dropdowns in a RAID log spreadsheet?

Score a risk by multiplying probability by impact on two 1 to 5 scales, which gives a top score of 25, then put dropdowns on Type and Status and a formula on the score column so nobody types it by hand. The scales and the 15 threshold below are our convention, not a published standard, so agree your own with the steering committee before the first review.

ScoreBandWhat to do
1 to 7LowKeep it in the workstream log and review on the normal rhythm
8 to 14MediumWrite a response with a date and an owner
15 to 25HighEscalate to the program log and review it at every steering meeting
A five by five grid of probability against impact, with scores from 1 to 25 colored in low, medium and high bands.
R-01 sits at probability 3 and impact 5, a score of 15, the first high cell.

The Excel file already has all of this built in. If you're setting up your own sheet, the steps are short:

  • Score formula: in the Score column, use =IF(B2="Risk",F2*G2,""), where B is Type, F is Probability and G is Impact. It leaves issues, assumptions and dependencies empty.
  • Dropdowns in Excel: select the Type cells, open Data, then Data Validation, set Allow to List and enter the four types. Repeat for Status.
  • Dropdowns in Google Sheets: select the cells and choose Insert, then Dropdown. Google's help page also describes Data, then Data validation, then Add rule for a list from a range.
  • Red flag on high scores: add a conditional formatting rule with the custom formula =$H2>=15 on the Score column.
  • Red flag on overdue reviews: use =AND($L2<TODAY(),$J2<>"Closed",$J2<>"Resolved") on the Review date column, where J is Status and L is the review date.

The formulas in this RAID log template cover rows 2 to 200, which leaves room for 199 entries before you extend the range. Keep the lists on their own tab, as in Tab 2, and point the dropdowns at it. That way, when someone adds a status later, every dropdown picks it up instead of just one column.

How do you check a RAID log before a review meeting?

Check a RAID log by looking for five failures before the meeting: entries without an owner, reviews that are overdue, risks without a response, high scores that haven't been escalated and resolved entries nobody has closed. Tab 3 counts the first four with COUNTIFS formulas and the last with a simple COUNTIFS on status, so you can read the result at a glance.

CheckWhat a failure meansFormula in Tab 3
Entries without an ownerNobody is keeping the entry moving=COUNTIFS(B2:B200,"<>",E2:E200,"")
Reviews past their dateThe log has stopped being reviewed=COUNTIFS(J2:J200,"Open",L2:L200,"<"&TODAY()) plus the same for "Escalated"
Risks without a responseThe risk is recorded but not managed=COUNTIFS(B2:B200,"Risk",I2:I200,"")
High risksScores of 15 or more that aren't on the program log=COUNTIFS(B2:B200,"Risk",H2:H200,">=15")
Resolved but not closedEntries waiting for a confirming review=COUNTIFS(J2:J200,"Resolved")

Atlassian lists two drawbacks of a RAID log that these checks target: it needs frequent updates, and logging every small question can bury the items that matter. The overdue check handles the first, and the high-risk count shows whether the second has happened. If a log has 60 open entries and four of them score above 15, those four are the meeting, not the other 56.

Before you share the RAID log
  • Every entry has an ID, a type and one named owner
  • Every open entry has a review date in the future
  • Every risk scoring 8 or more has a response with a date
  • Every entry scoring 15 or more is on the program log
  • Resolved entries are closed, with a note on why
  • The log sits in one place and everyone knows where

Which RAID log template format should you use?

The best RAID log template format depends on the job (the file here covers 2 of the 4 below): Excel when the log will be edited and checked with formulas, Word when it sits inside a plan or charter, Google Sheets when several people edit at once and slides when you present a summary to the steering committee. The download above covers Excel and Word, and the other two take one extra step each.

FormatBest whenHow to get it from this page
Excel (.xlsx)The log is edited weekly and checked with formulasDownload the Excel file, which has dropdowns, the score formula and the overdue flag
Word (.docx)The log is an appendix to a plan, charter or kickoff packDownload the Word file
Google SheetsSeveral people edit the log at the same timeIn Sheets, choose File, then Import, and upload the Excel file
PowerPoint or slidesYou summarize the log for a steering committeePaste the high-risk rows from Tab 1 onto one slide

Google's help page for importing files describes the path: open Sheets, choose File and Import, select the Excel file and pick whether to create a new spreadsheet or insert the tab as a new sheet. If you only need one tab, use Copy as text on the template card and paste it straight into a sheet.

Smartsheet publishes 5 RAID templates: a basic log, a matrix log with swimlanes by phase, a presentation, an Agile version with one sheet per category and a Gantt-style timeline, and an analysis report. They come in 7 formats: Excel, Word, PDF, PowerPoint, Google Docs, Google Slides and Google Sheets. That's a useful reference if you want a visual layout, though the licence terms of any template you take from another site are yours to check before you redistribute it.

If the log is going to live in a project tool, Asana's template shows the usual setup: custom fields for category, impact and status, a list view to see everything at once and task dependencies to mark which entries wait on others. Start in the spreadsheet if the process isn't settled yet; it's the cheaper place to be wrong. Moving a settled log into a tool is a simple import, and moving an unsettled one means rebuilding the fields.

How is a program RAID log template different from a project one?

A program RAID log template adds a workstream column and an ID prefix, and the program keeps one identical log per workstream plus a thinner program log above them. The project version is a single sheet. The program version is a set of sheets with identical columns, so a rollup is a filter instead of a rewrite.

DimensionProject RAID logProgram RAID log
Number of logsOneOne per workstream, plus a program log
IDsR-01, I-02A workstream prefix, such as HW-R-01 or TR-D-02
What moves upNothingEscalated entries and every dependency between workstreams
Who reviewsThe project manager and teamWorkstream leads weekly, the program manager and PMO before each steering meeting
Escalation ruleUsually noneWritten in the header, for example a score of 15 or more or any cross-workstream impact

Any RAID log entry scoring 15 or more moves up to the program log, and the 8 to 14 band stays in the workstream log with a dated response. The ID prefix is what keeps the rollup honest. When the program log copies R-01 from the hardware workstream, the entry keeps its ID, and the hardware log stays the record. Dependencies belong in both logs: the waiting workstream records the dependency so its lead sees it, and the program log carries every dependency between workstreams, since no single workstream sees them all. For the escalation rules and the full program method, see the RAID log guide. For the handoffs themselves, the project dependency matrix template lays them out as a grid.

A spreadsheet handles this well up to a handful of workstreams, but it's weak when an entry has to follow the state of work in other systems. The Program Manager doesn't replace the log, but it covers the dependency part: it maps links between work items across Jira and Asana, tracks blockers through an eight-state workflow with owners, due dates and the milestones each blocker holds, and keeps a decision log with options, rationale and approver. That means the D entries and the blockers can come from the tools your teams already use, rather than being retyped into a sheet.

What is the difference between a RAID log, a risk register and a RACI chart?

A RAID log tracks risks, assumptions, issues and dependencies in one sheet, a risk register tracks risks only and a RACI chart assigns who does what. They answer different questions, and a program usually uses all three.

DocumentWhat it coversUse it for
RAID logRisks, assumptions, issues and dependenciesOne working log per project or workstream
Risk registerRisks only, with analysis and responsesDetailed risk analysis, see our risk register guide
RACI chartWho is responsible, accountable, consulted or informedSettling ownership, see our RACI template

Give the owner column of the RAID log the same names that are accountable in the RACI chart, and the two documents stop contradicting each other. Our collection of program management templates links the rest of the set, including the status report template where the top entries from the log usually end up.

RAID log template FAQs

These answers cover the questions that come up when a team moves a RAID log template from a workshop into everyday use.

What should be on a RAID log?

A RAID log needs an ID, the type (risk, assumption, issue or dependency), a one-sentence description, one named owner, a status and a review date. Add the workstream, probability, impact, score, response and date raised once the log has more than a handful of entries.

Is there a free RAID log template in Excel?

Yes, there's a free RAID log template on this page, and it downloads as an Excel or Word file with no sign-up. The Excel file has dropdowns for type and status, a score formula and a flag for overdue reviews.

Can I use this RAID log template in Google Sheets?

Yes, you can use this RAID log template in Google Sheets. Choose File, then Import, and upload the Excel file. You can also use Copy as text on the template card and paste a tab straight into a sheet.

What does RAID stand for in a PMO?

RAID stands for risks, assumptions, issues and dependencies. Some teams use risks, actions, issues and decisions instead, which is how Smartsheet's help center and Asana describe the alternative. Write your version at the top of the log.

How often should you update a RAID log?

Update a RAID log at least monthly, which is the minimum Rebel's Guide to Project Management suggests for reviewing the whole log. Programs that move quickly usually review each workstream log weekly and the program log before each steering meeting.

What is the difference between a RAID log and a RACI chart?

A RAID log tracks what could go wrong or is waiting on someone. A RACI chart says who is responsible, accountable, consulted or informed for each task or decision. Use both, and keep the owner names consistent.